NBC Pulls Anti-Israel Ad From 'SNL' Special After Backlash Over $400 of 'Taxpayer Money'•Jensen Huang's Nvidia Comeback Could Usher in an 'Age of Resentment,' Warns Economist Steve Hanke•The Army Has Received Just 180 of Nearly 12,000 Abrams Rounds Due by Summer, and Taxpayers Are Still Paying•Why One Parent Swapped Christmas Gifts for Family Trips, and What It Actually Costs•Musk's Free SpaceX Shares for Every Child: A Gift Worth Watching, and a Reminder That Stakes Beat Subsidies•I Spent a Day Riding, Eating and Cleaning With Robots. Here's the Free-Market Scorecard.•A Budget Traveler's Honest Take on ASKY Airlines: Cheaper Than You Think, Less Consistent Than You'd Like•A Texas Relocation Broker Is Heading to Florida, and Her Clients Say the Tax Math Is Next•Booking Your First Cruise? Here Are the 7 Costs and Surprises Founders Should Plan For•Shake Shack's Holiday Shakes Ranked: The Christmas Cookie Is Sweet, the Hazelnut Chocolate Is Worth Watching•NBC Pulls Anti-Israel Ad From 'SNL' Special After Backlash Over $400 of 'Taxpayer Money'•Jensen Huang's Nvidia Comeback Could Usher in an 'Age of Resentment,' Warns Economist Steve Hanke•The Army Has Received Just 180 of Nearly 12,000 Abrams Rounds Due by Summer, and Taxpayers Are Still Paying•Why One Parent Swapped Christmas Gifts for Family Trips, and What It Actually Costs•Musk's Free SpaceX Shares for Every Child: A Gift Worth Watching, and a Reminder That Stakes Beat Subsidies•I Spent a Day Riding, Eating and Cleaning With Robots. Here's the Free-Market Scorecard.•A Budget Traveler's Honest Take on ASKY Airlines: Cheaper Than You Think, Less Consistent Than You'd Like•A Texas Relocation Broker Is Heading to Florida, and Her Clients Say the Tax Math Is Next•Booking Your First Cruise? Here Are the 7 Costs and Surprises Founders Should Plan For•Shake Shack's Holiday Shakes Ranked: The Christmas Cookie Is Sweet, the Hazelnut Chocolate Is Worth Watching•
Scale.
Sections
The outlet
Money

US Navy shipyard overhaul could top $200 billion and slip 50 more years

A new watchdog report says the repair plan for the Navy's four public shipyards will cost far more and take far longer than first planned. The program was originally estimated at 20 years and $21 billion, but the Navy now says it is building a multi-decade master plan.
SEP 29, 2026

The US Navy's plan to rebuild its four public shipyards is headed for a much bigger bill and a much longer timeline than first promised.

The Government Accountability Office said the Shipyard Infrastructure Optimization Program 'will surpass $200 billion and take over 50 more years to execute.' The report said the Navy 'underestimated the time needed' and 'did not fully account for the many challenges, uncertainties, and complex analyses needed to sufficiently plan for an endeavor of SIOP's magnitude.'

The effort is meant to fix poor conditions at Norfolk Naval Shipyard in Virginia, Pearl Harbor Naval Shipyard in Hawaii, Portsmouth Naval Shipyard in Maine, and Puget Sound Naval Shipyard in Washington. Those yards maintain the fleet's nuclear-powered submarines and aircraft carriers, but long-deferred maintenance has left them struggling to keep up with demand and created backlogs.

The GAO said the Navy started the optimization plan in 2018, but new risks and unplanned costs have expanded the scope. One major issue is seismic vulnerability at Puget Sound, where the Navy has identified over $1 billion in needed facility retrofits and new construction since 2023 to reduce newly assessed seismic risks.

The report also said many of the facilities were built between 80 and 120 years ago and have deteriorated. In some cases, that has created safety risks in buildings that are still in use for ship maintenance.

The GAO recommended that Congress require the Navy to 'annually report consolidated, standardized status updates' on cost and schedule. It also called for future reviews of requirements and resources, plus clearer documentation of roles and responsibilities across the program.

A Navy official said the original estimate of 20 years and $21 billion was only a preliminary assessment that has since evolved. The official said the program has already delivered 'tangible readiness results' and that the Navy is 'incorporating their recommendations' as it develops a multi-decade master plan.

The math is simple: when a public works project grows from a preliminary $21 billion estimate into a potential $200 billion burden, taxpayers pay for the delay. And when the state underestimates complexity upfront, the bill is not just financial — it is measured in readiness, maintenance backlogs, and decades of disruption to the fleet.

LK
Laura Kessler
Money Columnist

Laura Kessler covers capital, taxes, markets and the economy — a founder's guide to the numbers, from runway to revenue.

More from Money

A Budget Traveler's Honest Take on ASKY Airlines: Cheaper Than You Think, Less Consistent Than You'd Like
A Texas Relocation Broker Is Heading to Florida, and Her Clients Say the Tax Math Is Next
NBC Pulls Anti-Israel Ad From 'SNL' Special After Backlash Over $400 of 'Taxpayer Money'