Oracle has sent a force majeure notice to the developer of Project Jupiter, the Stargate data center campus in New Mexico, Bloomberg first reported. The notice would allow Oracle to delay payments if the facility misses its 2028 target to come online.
Oracle is not seeking to exit as the campus's main tenant, according to Bloomberg's sources. Oracle said in a statement to CNBC that 'Project Jupiter remains on our planned schedule' and that it is 'fully committed to New Mexico and confident in our path forward.' Blue Owl Capital, whose unit received the notice, said the notice 'does not change the financial commitments to this multi-year project.'
The campus is designed to handle 2.45 gigawatts. It is meant to run on gas-powered fuel cells from Bloom Energy, which makes reliable gas supply central to the timeline. That supply chain has not cooperated.
An Energy Transfer pipeline intended to deliver gas to the site has been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits for the line. In August, Bloomberg reported that the pipeline's route had been changed after those rejections. A separate air-quality permit for the fuel cell system is still pending, and the state environment department faces a November 23 deadline to decide.
The notice lands as AI data center construction faces growing scrutiny and as developers take on steep costs to build capacity for customers like OpenAI. Project Jupiter is one of the flagship Stargate sites that Oracle, OpenAI, and SoftBank announced with President Donald Trump early in his second term.
The math is simple. Big AI projects are not just about chips and demand. They are about permits, fuel, and financing that can survive delays. When one piece slips, the burden can move to tenants, lenders, and ultimately customers.
Founders and operators chasing the AI boom should read this as a warning about the administrative state and infrastructure risk. A campus can look fully committed on paper and still be one permit away from pain. In capital-heavy markets, timing is not a detail. It is the business model.