Here's the playbook from inside one of the most closely watched capital allocation problems in business. John Felton, Chief Financial Officer of Amazon Web Services, is responsible for answering a question nobody can answer cleanly: how much should you bet on AI when no one knows how much demand there will be?
At a September staff meeting, Felton made his view plain. According to a recording of the meeting obtained by Business Insider, he said the company's planning process was 'too cumbersome and too sequential' and needed to become 'much more real time.' 'The point forecast is inherently going to be wrong,' he said.
His background explains the approach. Before moving to AWS in 2024, Felton spent roughly two decades helping Amazon build its vast retail and delivery network, where betting too much or too little on future demand could be costly. Former Amazon executives describe him as even-keeled and funny, and say he wants to understand what has to happen on the ground for an investment to work, not just the financial case.
His investment theory is simple. 'Land, power and permitting take years, so we commit to those early,' Felton told Business Insider. 'Everything we can buy later, we buy later, because waiting gives us more information and keeps our choices open.' The goal, he said, is to make 'the right decision at the last responsible moment.' In his words: 'If the demand is not there, we do not place the order.'
The demand signals are concrete. AWS uses customer commitments as its clearest indicator, and its backlog of cloud contracts stood at $578 billion as of the third quarter, growing at a triple-digit rate. AWS revenue has accelerated for six straight quarters, most recently growing 39% to $46 billion.
Felton is also focused on cost. 'The math is hard,' he said at the September meeting. 'Are we the lowest-cost kind of provider? How do you measure that?' One answer is a wider menu of data center designs and server configurations, which gives the company more ways to add capacity instead of a single multi-year commitment. Prasad Kalyanaraman, an AWS infrastructure leader, said that approach would avoid spending 'three years in advance on an uncertain forecast.'
The scrutiny extends to electrical equipment. In a recent procurement of power-distribution cabinets, AWS weighed suppliers' factory capacity and tariff exposure, not just price. Internally, the company evaluated a potential deal with manufacturer Jabil that could slash annual costs by $300 million, according to an internal document reviewed by Business Insider.
The lesson for founders is that capital discipline is a sequencing question. Commit to the assets with long lead times, where delay is costly. Keep everything else flexible until customers have shown what they will pay for. Don't let a forecast, however confident, make the purchasing decision for you.
The market will test that discipline. Hundreds of billions of dollars are riding on AI demand, and an overbuilt capacity bet lands on shareholders, lenders and, in the end, on the broader economy. The free-market answer is not to spend more to feel bold. It is to let paying customers, not projections, decide when the money goes out the door.